Ash mixing system in thermal power plant Kakanj, Bosnia and Herzegovina

In thermal power plant Kakanj, BiH, renovation of mixing system for ash remaining after combustion of coal was performed. Waste ash is mixed with the waste water, which is collected at the plant, and transferred via the transport of ash to landfill waste site. Due to the useage of wastewater, which is in this way re-used, project has also ecological significance.

Project: The ash and sludge mixing system TE Kakanj, Bosnia and Herzegovina
Execution time: Year 1999
Role on project: Project management, automation control and monitoring software
Total investment cost: 800.000 EUR

Ash mixing system in thermal power plant Kakanj, Bosnia and Herzegovina

In thermal power plant Kakanj, BiH, renovation of mixing system for ash remaining after combustion of coal was performed. Waste ash is mixed with the waste water, which is collected at the plant, and transferred via the transport of ash to landfill waste site. Due to the useage of wastewater, which is in this way re-used, project has also ecological significance.

Project: The ash and sludge mixing system TE Kakanj, Bosnia and Herzegovina
Execution time: Year 1999
Role on project: Project management, automation control and monitoring software
Total investment cost: 800.000 EUR