Landfill excavators in Trbovlje thermal power plant

In thermal power plant Trbovlje renovation of two landfill loading and unloading machines was performed. These two machines dispose a surplus of coal from a mine or send coal from landfill, throuh transport system to the power plant, when coal mine is not working.

Entire electrical equipment on the machine has been replaced. Replaced were all electrical switchgears, all electrical connection cables, and performed automation control system with process PLC. Machine control is implemented through the control panel and joysticks in the cabin.

Machine can be operated fully automatically. On the control panel area there is seting for automatic operation. Thee machine is placed on the starting point. By turning the autopilot on, machine automatically begins operation, such as coal deposit collection of coal dumps.

Project: Renovation of landfill machine KRB 9
Execution time Year 1997
Role on Project: Project Manager, software for operater control and machine automation control
Total investment cost: 230.000 EUR

 

Project: Renovation of landfill machine KRB 10
Execution time Year 1998
Role on Project: Project management, software for operater control and machine automation control
Total investment cost: 230.000 EUR

 


Landfill excavators in Trbovlje thermal power plant

In thermal power plant Trbovlje renovation of two landfill loading and unloading machines was performed. These two machines dispose a surplus of coal from a mine or send coal from landfill, throuh transport system to the power plant, when coal mine is not working.

Entire electrical equipment on the machine has been replaced. Replaced were all electrical switchgears, all electrical connection cables, and performed automation control system with process PLC. Machine control is implemented through the control panel and joysticks in the cabin.

Machine can be operated fully automatically. On the control panel area there is seting for automatic operation. Thee machine is placed on the starting point. By turning the autopilot on, machine automatically begins operation, such as coal deposit collection of coal dumps.

Project: Renovation of landfill machine KRB 9
Execution time Year 1997
Role on Project: Project Manager, software for operater control and machine automation control
Total investment cost: 230.000 EUR

 

Project: Renovation of landfill machine KRB 10
Execution time Year 1998
Role on Project: Project management, software for operater control and machine automation control
Total investment cost: 230.000 EUR